Days one and two
Offloading dominates. Panels are numbered and stacked in reverse order of use, so the first hour is usually spent moving the last boxes out of the way.
- Weathertight in three to five days is realistic for a trained crew.
- Lifting equipment is the gating resource, not labour.
- The first day is consumed by offloading and sorting.
By the end of day one a good crew has the floor cassettes down and squared. Day two is walls, bracing and the first pass at alignment — do not skip the diagonal measurements.
Days three to five
Roof structure and covering follow, then windows and doors. This is when the building becomes weathertight and the schedule risk drops sharply.
Allow half a day for the airtightness tape and membrane detailing. It is invisible work with the biggest effect on how the finished house performs.
Where days disappear
Missing fixings, a telehandler that arrives a day late, and site access that requires moving a delivery twice. Confirm the lifting plan in writing before the container ships.
Ground conditions are the other variable. A level, compacted pad removes a whole day of shimming and re-levelling.