Fix the comparison point
Ex-works means you collect from the factory. FOB adds loading and inland transport to port. CIF adds freight and insurance. Installed adds crane, crew and commissioning.
- Normalise every quote to the same delivery point before comparing.
- Ask what is excluded — exclusions are where the real difference hides.
- Installation labour is the most commonly omitted line.
Two quotes that differ by 30% are often just quoted at different incoterms. Re-state every price as delivered to your site with duties paid before you compare anything.
Read the exclusions
Foundations, permits, crane hire, power connection and final cleaning are the five most commonly excluded items. Each one is real money, and together they can exceed the difference between competing quotes.
Ask for the exclusion list in writing, then price it yourself with local suppliers. That exercise usually reveals which quote is genuinely cheaper.
Payment terms and risk
A large deposit with no milestone documentation transfers all the risk to you. Tie payments to verifiable events: drawings approved, frame complete with photos, unit ready for shipment.
Where possible hold a retention until handover documentation is delivered. It is a normal commercial request and a good test of how organised the supplier is.