Where the time actually goes
On a traditional build, structure, envelope and fit-out run in sequence. Prefab moves the last two into a factory that works in parallel with foundations and services.
- Prefab compresses construction, not permitting.
- Overlapping factory work with site work is where the real gain sits.
- Late design changes erase the advantage faster than anything else.
Design and permitting are unchanged. If plan check takes twelve weeks, it takes twelve weeks for both methods — so a prefab advantage only starts after approval.
The overlap window
Maximum benefit comes when factory production starts as soon as drawings are approved, not after foundations are complete. That requires a supplier willing to commit to a production slot before the site is ready.
Buyers who wait for a finished slab before ordering modules give back most of the schedule saving — typically four to eight weeks.
What erases the advantage
Change orders after production starts, delayed service connections and late crane bookings. Each one removes a week or more from the gain.
Weather does not disappear either: groundworks for both methods are exposed to it, and a wet winter can delay a modular project just as easily as a traditional one.