Structural package
You need sealed structural drawings, a foundation design matched to your soil report, and calculations for snow, wind and seismic loads at your address — not a generic regional figure.
- Stamped structural drawings are non-negotiable in almost every market.
- Thermal calculations decide whether your wall build-up is accepted.
- Ask for the documents before you sign, not after.
If the supplier cannot stamp for your jurisdiction, budget for a local engineer to review and seal. That review typically takes two to four weeks and is worth scheduling first.
Energy and envelope
Most reviewers want a wall and roof assembly with U-values, plus glazing performance. Manufacturers that publish tested assemblies move through plan check far faster than those supplying one-off letters.
Fire ratings matter on boundary walls. A one-hour assembly is common where the unit sits within three feet of a property line.
Site and services
A site plan showing setbacks, the utility trench route and drainage is required everywhere. Add a geotechnical report if the ground is fill or slope.
Finally, keep the installation manual. Some jurisdictions treat a prefab install as a site-built activity and will inspect the connections, not just the factory output.